Drywall is priced per m². The rate depends on the number of board layers, the insulation and the shape of the room — a straight partition sits at the bottom of the range, a curved ceiling with concealed lighting at the top.

Labour prices

WorkTypical labour
Partition, single boardingHUF 6,000 – 11,000 / m²
Partition, double boarding + acoustic insulationHUF 9,000 – 15,000 / m²
Suspended ceilingHUF 6,500 – 12,000 / m²
Dry lining, boxing in pipeworkHUF 6,000 – 10,000 / m²
Taping and skimming for paintHUF 1,800 – 3,500 / m²
Built-in niche or shelvingHUF 20,000 – 60,000 each

Board, profiles, mineral wool and filler are normally not included. For a 10 m² partition that's roughly HUF 40,000 – 90,000 in materials.

What can you hang on it?

The most common question, and it's decided before boarding. Wherever a TV, basin, kitchen unit or grab rail will go, noggins or extra profiles must be fitted first. Retrofitting with special plasterboard fixings works but carries a fraction of the load. Say up front what goes where — it doesn't cost more, it just needs planning.

Acoustic performance

  • Empty, single-boarded wall: weak; speech carries through.
  • Double-boarded with mineral wool: around 45–50 dB, the right answer between a bedroom and a living room.
  • The smallest gap ruins it — junctions with floor and ceiling matter most.
  • Services (pipes, socket boxes) in the wall reduce performance; offset boxes rather than placing them back to back.

Frequently asked questions

What does a plasterboard partition cost per m²?

Single boarding is typically HUF 6,000 – 11,000 / m² in labour. Double boarding with acoustic insulation runs HUF 9,000 – 15,000 / m².

What does a suspended ceiling cost?

Typically HUF 6,500 – 12,000 / m². Concealed lighting, curves and stepped details push it to the upper half.

Can I hang heavy items on plasterboard?

Yes, if reinforcement is fitted before boarding. Retrofitted special fixings work but carry much less load.

How long does it take?

A 10 m² partition including filling typically takes 2–3 days, plus drying time before painting.